Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 3 Current »

Project Board

https://github.com/orgs/nephio-project/projects/2/views/1

Functional Scope - Planned

  • Sprint 1
    • Nephio Up and Running
    • User Story 1: Deploy 5G core Network Functions (NFs) with CUPS (Control user-plane separation) architecture.
  • Sprint 2
  • Sprint 3
  • Sprint 4
    • User Story 4: Upgrade to user plane that automatically implies and upgrade to control plane.
  • Sprint 5
    • Bug Fixes

Execution Plan

SprintsDurationDateSprint GoalSprint Deliverables/Outcomes
Sprint 12 weeks

 

Setting stage & Bootstrap
  1. Setting up build pipelines with PROW including build, test, CLA validation . Setting up owners.
  2. Clarify requirements for further execution. These are in the areas of UI, end to end test bed, ultimate goal of  R1 ( like making end to end call etc)
  3. Define and understand  the process . Github boards, workflows and PR process.
  4. Design and implement common libraries that would make rest of R1 execution faster . Some are merged (eg: KPT File) and some are in the code review cycle.
  5. Design  and implementation of common function run time. We have a few iterations on this and made progress This will again make rest of the execution a bit simpler.
  6. Create initial CRDs and packages for free5gc functions.
  7. We have multiple PRs in progress which are in the review cycle.
Sprint 22 weeks

  

  1. Complete the work on common libraries and other foundational work items such as function run time
  2. Have a version of free5gc controllers and operator running.
  3. Make progress in the creation of test bed for Nephio Deployment
  4. Be ready to start integration testing from  sprint 3.

Sprint 32 weeks

  



Sprint 42 weeks

  



Sprint 51 week

  



  • No labels