Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Execution Plan

SprintsDurationDateSprint GoalSprint Deliverables/Outcomes
Sprint 12 weeks

to  

Setting stage & Bootstrap
  1. Setting up build pipelines with PROW including build, test, CLA validation . Setting up owners.
  2. Clarify requirements for further execution. These are in the areas of UI, end to end test bed, ultimate goal of  R1 ( like making end to end call etc)
  3. Define and understand  the process . Github boards, workflows and PR process.
  4. Design and implement common libraries that would make rest of R1 execution faster . Some are merged (eg: KPT File) and some are in the code review cycle.
  5. Design  and implementation of common function run time. We have a few iterations on this and made progress This will again make rest of the execution a bit simpler.
  6. Create initial CRDs and packages for free5gc functions.
  7. We have multiple PRs in progress which are in the review cycle.
Sprint 22 weeks

to  

  1. Complete the work on common libraries and other foundational work items such as function run time
  2. Have a version of free5gc controllers and operator running.
  3. Make progress in the creation of test bed for Nephio Deployment
  4. Be ready to start integration testing from  sprint 3.

Sprint 32 weeks

to  



Sprint 42 weeks

to  



Sprint 51 weeks

to  

Bug fixes